Dates | Contents | Box | Volume | ||
---|---|---|---|---|---|
Accretion: B0711-85 |
|||||
1878 November-1880 May | Monthly and Final Estimates for Work Completed in Construction of Dock at Sing Sing Prison by John O'Brien, Contractor | 1 | 1 |
1884 October-1885 July | Monthly and Final Estimates for Work Completed in Construction of Drains and Relaying of Concrete Flooring in Basement of Buffalo State Asylum by Charles E. Williams, Contractor | 1 | 2 |
1885 | Final Estimates for Work Completed in Construction of a Sewer for Buffalo State Asylum by Charles E. Williams, Contractor | 1 | 3 |
1885 April-1886 May | Monthly Estimates for Construction of New House and Barn (Location Unknown) by Multiple Contractors | 1 | 4 |