Contains records relating to capital construction projects involving the construction of, additions to, and rehabilitation of, buildings in the New York State school system. Many of these projects concern the maintenance of the New York State School for the Blind in Batavia and the New York State School for the Deaf in Rome. Other projects include improvements to the State Education Building in Albany and the construction and rehabilitation of schools located on Native American reservations. Included are blueprints, specifications of labor and materials required, correspondence, requests for bids, and copies of contracts.

  

Dates Contents Box Folder

Accretion: W0105-93
1970 April-December Capital construction - State Education Building - Dehumidification Tanks 2 1
1968 May-1972 May Capital construction - State Education Building - Passenger Elevators - Automation of Nos. 5, 6, 7, 8 2 2
1969 April-May Capital construction - State Education Building - Electrical Capacity - Main Building and Addition 2 3
1968 August-1969 April Capital construction - State Education Building - Heating and Air Conditioning- Phase 1 Replacement of Elevators Nos. 5, 6, 7, 8 and Appurtenant Work 2
1962 June-August Capital construction - State Education Building - Exterior Lighting (Installation of) 2 4
1955 June-1969 February Capital construction - State Education Building - Museum - Conversion of 4th Floor 2 5
March 1960-March 1965 Capital construction - State Education Building - Fallout Shelters - General 2 6
1963 January-April Capital construction - State Education Building - Fallout Shelters 2 7
1970 May-July Capital construction - State Education Building - New Offset Press for Printing Plant 2 8
1971 July-December Capital construction - State Education Building - Storm Sewer (Engine Room) 2 9
1971 August Capital construction - State Education Building - Water Treatment System 2 10
1969 April Capital construction - State Education Building - Blueprints for Replacement of Elevators 5, 6, 7, 8 and Appurtenant Work 2
1971 October-1973 June Capital construction - State Education Building - Lighting System - Kingsbridge Armory (Professional Licensing Exams) 2 11
1970 February-1971 September Capital construction - State Education Building - Museum Exhibit Center - 60 Commerce Ave. 2 12
1954 November-1961 November Capital construction - State Education Building - Addition (Offices) 5 1
1959 February-1960 August Capital construction - State Education Building - Addition (Offices) 5 2
1956 April-1959 April Capital construction - State Education Building - Addition to building - Building Committee 5 3
1956 June-1957 October Capital construction - State Education Building - Addition to building - Milton Musicus's notes 5 4
1962 October-1965 November Capital construction - State Education Building - Computer site preparation 5 5
1967 January-1968 March Capital construction - State Education Building - Data processing facilities 5 6
1967 December-1968 January Capital construction - State Education Building - Driveway 5 7
1966 April-1967 January Capital construction - State Education Building - New cars in passenger elevator 5 8
1962 January-February Capital construction - State Education Building - Fire alarm boxes 5 9
1958 December Capital construction - State Education Building - Fire safety 5 10
1966 July-August Capital construction - State Education Building - Hoistway doors (Install) 5 11
1966 June-1967 November Capital construction - State Education Building - Loading dock (Resurface of) 5 12
1965 May-1966 February Capital construction - State Education Building - Library stack elevator #12 (Repairs to) 5 13
1967 April-August Capital construction - State Education Building - Adequate lighting (Commissioner's office) 5 14
1966 January-1967 November Capital construction - State Education Building - Adequate lighting - State Library 5 15
1966 June-1968 August Capital construction - State Education Building - Opening in walls and ceilings (rehabilitate) 5 16
1968 January-August Capital construction - State Education Building - Museum panelboard (replace) 5 17
1968 May-August Capital construction - State Education Building - Painting 5 18
1959 September-1964 July Capital construction - State Education Building - Planting of trees 5 19
1967 March-1968 October Capital construction - State Education Building - Illumination (Regents Room) 5 20
1967 September-November Capital construction - State Education Building - Roof 5 21
1965 May-July Capital construction - State Education Building - Weatherstrip windows 5 22
1955 August-1968 July Capital construction - State Education Building - Air conditioning - Chancellor's Hall 5 23
1969 May-1974 July Capital construction - Batavia - Demolition of Boiler House 7 1
1973 September-1974 August Capital construction - Batavia - Door Hardware 7 2
1973 July-1974 August Capital construction - Batavia - Park Lights 7 3
1973 December-1975 March Capital construction - Batavia - Exit - Roller Rink 7 4
1973 August Capital construction - Batavia - Alterations for Improved Fire Safety 7
1973 February-1974 May Capital construction - Rome - Cracked Ceilings 7 5
1974 February-September Capital construction - Rome - Fire Safety Building No. 9; Emergency Lighting Building No. 11 7 6
1973 December-1975 June Capital construction - Rome - Roof Repairs 7 7
1972 May-1973 June Capital construction - St. Regis Mohawk Indian School - Boilers 8 1
1972 February-1973 April Capital construction - St. Regis Mohawk Indian School - Rehab. of Various Rooms and Appurtenant Work (Construction, Heating, and Sanitary) 8 2
1971 July-1973 August Capital construction - St. Regis Mohawk Indian School - Rehab. of Various Rooms and Appurtenant Work (Electric) 8 3
1967 May-1972 September Capital construction - St. Regis Mohawk Indian School - Roof Repairs 8 4
1971 August-1973 March Capital construction - Tuscarora Indian School - Boilers 8 5
1971 September-1972 December Capital construction - Tuscarora Indian School - Interior Plastering, Painting and Tiling 8 6
1970 November-1973 March Capital construction - Tuscarora Indian School - Roof Repairs 8 7
1972 July-1973 February Capital construction - Tuscarora Indian School - Repairs to Sewerage System 8 8
1972 May Capital construction - St. Regis Mohawk Indian School - Rehabilitation of Electrical System and Appurtenant Work 8
1972 May Capital construction - St. Regis Mohawk Indian School - Rehabilitation of Various Rooms and Appurtenant Work 8
1970 September Capital construction - St. Regis Mohawk Indian School - Rehabilitation of Toilet Rooms 8
1953 April-1974 July (bulk 1953 April-1957 June) Capital construction - Allegany Indian Reservation - General Correspondence 10 1
1958 November-1966 September Capital construction - Allegany Indian Reservation - New Elementary School Building 10 2
1953 January-1957 February Capital construction - Allegany Indian Reservation - Transfer of Old Buildings 10 3
1954 April-1966 March (bulk 1954 April-1961 November) Capital construction - Cattaraugus Indian Reservation - General Correspondence 10 4
1954 April-1961 August Capital construction - Onondaga Indian Reservation - General Correspondence 10 5
1954 August-1967 September Capital construction - Onondaga Indian Reservation - General Repairs and Rehab. 10 6
1962 November-1965 July Capital construction - Onondaga Indian Reservation - Fallout Shelter 10 7
1965 January-1966 May Capital construction - Onondaga Indian Reservation - Heating and Electrical Work 10 8
1963 April-1964 September Capital construction - Onondaga Indian Reservation - Parking Lot 10 9
1954 October-November Capital construction - Poospatuck Indian Reservation - General Correspondence 10 10
1954 June-1967 March Capital construction - St. Regis Indian Reservation - General Correspondence 10 11
1957 February-1958 November Capital construction - St. Regis Indian Reservation - General Repairs and Rehab. 10 12
1962 March-1965 April Capital construction - St. Regis Indian Reservation - Replacement of Boiler 10 13
1962 June-1965 July Capital construction - St. Regis Indian Reservation - Fallout Shelter 10 14
1967 June-1969 September Capital construction - St. Regis Indian Reservation - Painting 10 15
1960 August-1968 December Capital construction - St. Regis Indian Reservation - General Repairs and Rehab. 10 16
1967 June-1969 March Capital construction - St. Regis Indian Reservation - Repair and Replacement of Sidewalk 10 17
1954 March-1967 June Capital construction - Tuscarora Indian Reservation - General Correspondence 10 18
1954 June-1967 July Capital construction - Tuscarora Indian Reservation - General Repairs and Rehab. 10 19
1963 January-1965 July Capital construction - Tuscarora Indian Reservation - Fallout Shelter 10 20
1967 June-1969 August Capital construction - Tuscarora Indian Reservation - Fence Painting and Repairs 10 21
1967 June-1968 December Capital construction - Tuscarora Indian Reservation - Blacktop Road 10 22
1963 May-1967 March Capital construction - Tuscarora Indian Reservation - Roof Repairs 10 23
1964 November-1965 April Capital construction - Tuscarora Indian Reservation - Sanitary Work 10 24
1967 June-1968 December Capital construction - Tuscarora Indian Reservation - Window Frames 1967 June-1968 December 10 25
1963 February-1964 August (bulk 1963 February-November) Capital construction - Commissioner's residence - Fire Protection 13 1
1964 June-1965 February Capital construction - Commissioner's residence - Kitchen 13 2
1959 December-1966 September Capital construction - Commissioner's residence - Planting 13 3
1968 May-1969 July Capital construction - Commissioner's residence - Radiators 13 4
1968 June-1969 November Capital construction - Commissioner's residence - Roof Rehabilitation 13 5
1968 November-1970 September Capital construction - State Education Building - New Computer Room 13 6
1958 March-1966 April Capital construction - State Museum - Protection of Shaft to Rotunda 13 7
1964 June-1970 August Capital construction - State Education Building - Balustrades and Steps (Restoration of) 13 8
1968 November Capital construction - State Education Building - Pile Driving, Vibration Readings 13 9
1968 June-1970 January Capital construction - State Education Building - Valve Station 13 10
1968 April-1969 October Capital construction - State Education Building - Rewiring and New Fixtures 13 11
1966 December-1969 July Capital construction - State Education Building - Adequate Wiring - Chancellors Hall 13 12
1971 February-1972 September Capital construction - Rome - Demolition - Phase IV 26 1
1970 June-November Capital construction - Rome - Demolition - Phase III 26 2
1972 February-June Capital construction - Rome - Fencing 26 3
1971 August-1973 July Capital construction - Rome - Grounds lighting 26 4
1973 January-1974 March Capital construction - Rome - Swimming pool 26 5
1973 February-October Capital construction - Rome - Sewing room exits 26 6
1969 April-1971 May Capital construction - Rome - Superintendent's residence (Storage space) 26 7
1957 December-1973 August Capital construction - Rome - Land acquisition 26 8
1966 May-August Capital construction - Rome - Land acquisition - Map 1 26 9
1966 May-1968 September Capital construction - Rome - Land acquisition - Map 2 26 10
1966 May-1967 June Capital construction - Rome - Land acquisition - Map 3 26 11
1966 February-1968 March Capital construction - Rome - Land acquisition - Map 4 26 12
1966 May-1969 February Capital construction - Rome - Land acquisition - Map 5 26 13
1966 February-October Capital construction - Rome - Land acquisition - Map 6 26 14
1966 May-August Capital construction - Rome - Land acquisition - Map 7 26 15
1966 May-October Capital construction - Rome - Land acquisition - Map 8 26 16
1966 September-November Capital construction - Rome - Land acquisition - Map 9 26 17
1967 December-1968 April Capital construction - Rome - Land acquisition - Map 10 26 18
1967 December-1969 January Capital construction - Rome - Land acquisition - Map 11 26 19
1967 December-1969 January Capital construction - Rome - Land acquisition - Map 12 26 20
1967 August-1969 January Capital construction - Rome - Land acquisition - Map 13 26 21
1967 August-1969 March Capital construction - Rome - Land acquisition - Map 14 26 22
1967 August-1969 February Capital construction - Rome - Land acquisition - Map 15 26 23
1967 December-1969 January Capital construction - Rome - Land acquisition - Map 16 26 24
1968 December-1972 November Capital construction - Rome - Acquisition of property - Maps 17-25 26 25
1970 May-1971 November Capital construction - Rome - Land acquisition - Map 17 26 26
1971 March-1972 February Capital construction - Rome - Land acquisition - Map 18 26 27
1970 May-1973 March Capital construction - Rome - Land acquisition - Map 19 26 28
1970 May-1971 December Capital construction - Rome - Land acquisition - Map 20 26 29
1970 May-1972 June Capital construction - Rome - Land acquisition - Map 21 26 30
1970 May-1973 April Capital construction - Rome - Land acquisition - Map 22 26 31
1969 October-1973 January Capital construction - Rome - Land acquisition - Map 23 26 32
1971 May-1972 February Capital construction - Rome - Land acquisition - Map 24 26 33
1970 May-1971 December Capital construction - Rome - Land acquisition - Map 25 26 34
1971 April-1972 September Capital construction - Rome - Land acquisition - Map 26 26 35
1972 May-1975 August Capital construction - Tuscarora Indian School - Rehabilitation work of interior and exterior 28 1
1972 May-1974 August Capital construction - Onondaga Indian School - Rehabilitation of basement area 28 2
1973 April Capital construction - Onondaga Indian School - Construction, HVAC and electrical work 28
1973 April-July Capital construction - Onondaga Indian School - Tractor storage area 28 3
1970 January-October Capital construction - St. Regis Indian School - Bus garage and shower stalls 28 4
1969 October-1972 January Capital construction - St. Regis Indian School - Rehabilitation of toilet rooms 28 5
1972 May-1974 July Capital construction - St. Regis Indian School - Rehabilitation of classrooms 28 6
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Construction 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - HVAC work 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Plumbing work 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Electric work 28
1974 February Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Plumbing work 28
1974 February-March Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Construction work 28
1974 February Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Electric work 28
1974 February Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - HVAC work 28
1973 September Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Basement floor plan 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Construction work 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Basement plan 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - HVAC work 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Plumbing work 28
1974 January Capital construction - Tuscarora Indian School - Rehabilitation of interior and exterior - Electric work 28
1965 December-1968 April Capital construction - Batavia - Superintendent's residence 29 1
1971 October-1972 December Capital construction - Batavia - Superintendent's residence - Chimney repairs and Severne Hall - Masonry repairs 29 2
1968 December-1971 June Capital construction - Batavia - Soundproof doors 29 3
1970 April-1971 September Capital construction - Batavia - Severne Hall - Brickwork 29 4
1972 May-1973 August Capital construction - Batavia - Brickwork and rehabilitation of steps 29 5
1971 July-1972 August Capital construction - Batavia - Filtration plant (swimming pool) 29 6
1967 August-1968 January Capital construction - Batavia - Former superintendent's residence 29 7
1973 February-March Capital construction - Batavia - Superintendent's residence - Drain tile 29 8
1969 December-1971 December Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Construction 29 9
1969 October-1971 December Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Electric 29 10
1969 October-1973 March Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Heating 29 11
1969 November-1972 April Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Sanitary 29 12
1968 July-1973 February Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex 29 13
1969 August Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Construction 29
1969 August Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Heating 29
1969 August Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Sanitary 29
1969 March Capital construction - Batavia - Heating plant, maintenance shops, vehicle and equipment storage complex - Construction 29
1968 April Capital construction - Batavia - Vehicle and equipment storage building - Construction 29
1968 April Capital construction - Batavia - Vehicle and equipment storage building - Heating 29
1968 April-May Capital construction - Batavia - Vehicle and equipment storage building - Sanitary 29
1968 April Capital construction - Batavia - Vehicle and equipment storage building - Electric 29
1964 January-1967 August Capital construction - Rome and Batavia - Escape windows 30 1
1959 November-1963 October Capital construction - Rome and Batavia - Primary building 30 2
1964 October-November Capital construction - Rome and Batavia - Burglar alarm system 30 3
1965 August-1968 July Capital construction - Rome - Superintendent's residence 30 4
1966 June-1968 August Capital construction - Rome and Batavia - Repair coal bunker 30 5
1961 April-1965 October Capital construction - Batavia - Superintendent's residence 30 6
1949 December-1954 December Capital construction - Rome and Batavia - Gymnasium building 30 7
Capital construction - Videotape "...gestion des dechete radioacti...(SECAM)" 30
1965 January-November Capital construction - Rome - Replacement data 30 8
1963 January-1964 November Capital construction - Rome - Replacement data 30 9
1954 November-1962 December Capital construction - Rome - Replacement data 30 10
1967 January Capital construction - Rome - Superintendent's residence - Heating 30
1967 January Capital construction - Rome - Superintendent's residence - Construction 30
1967 January Capital construction - Rome - Superintendent's residence - Sanitary Work 30
1959 March-1966 August Capital construction - Rome - Installation of boiler 30 11
1959 June-1965 December Capital construction - Specifications for labor and materials 30
1972 May-1973 August Capital construction, FY 1973-1974 36 1
1969 May-1972 September Capital construction, FY 1972-1973 36 2
1970 March-1971 February Capital construction, FY 1971-1972 36 3
1967 November-1973 March Capital construction, FY 1970-1971 36 4
1968 March-1971 July Capital construction, FY 1969-1970 36 5
1961 October-1967 February Proposed 5-year capital construction program (FY 1966-1967 to 1969-1970) 36 6
1965 October-1970 January Capital construction, FY 1965-1966 36
1963 April-1967 April Capital construction, FY 1965-1966 36 7
1967 May-1968 March Capital construction, FY 1967 36
1964 June-1970 June Capital construction, FY 1966-1967 36 8
circa 1963-1967 Proposed five-year capital construction program, 1963-1964 to 1967-1968. 36 9
1965 September-1968 April Capital construction, FY 1967-1968 36 10
1967 April-1969 April Capital construction 36 11
1967 September-1973 July Capital construction, FY 1968-1969 36 12
1971 April-1972 November Capital construction, FY 1971 36 13
1948 August-October Capital construction, FY 1949-1950 36 14
1971 July-1974 June Capital construction - Rome - Administration and classroom building 41 1
1971 June Capital construction - Rome - Blueprints - Improvement of grounds, athletic fields, and entrance road 41 2
1965 July-1972 July Capital construction - Rome - Administration and classroom building 41 3
1969 February-1971 August Capital construction - Rome - Administration and classroom building 41 4
1963 June Capital construction - Rome - Vehicle and food storage building 41 5
1968 August-1969 September Capital construction - Rome - Temporary kitchen, dining, administration and classroom facilities, building 2 41 6
circa 1968 Capital construction - Rome - Equipment and furnishings for administration, high school, library wing of new school complex 41 7
1965 September-1974 August Capital construction - Rome - Athletic facilities 41 8
1969 May-1973 September Capital construction - Rome - Administrative and classroom building - Electric 41 9
1969 May-1972 May Capital construction - Rome - Administrative and classroom building - Elevator 41 10
1969 June-1972 February Capital construction - Rome - Administrative and classroom building - Equipment 41 11
1969 May-1972 March Capital construction - Rome - Administrative and classroom building - Food service equipment 41 12
1969 May-1974 November Capital construction - Rome - Administrative and classroom building - Heating 41 13
1969 April-1973 March Capital construction - Rome - Administrative and classroom building - Laundry equipment 41 14
1969 May-1973 September Capital construction - Rome - Administrative and classroom building - Sanitary 41 15
1968 December-1971 July Capital construction - Rome - Administrative and classroom building - Storm sewer lines 41 16
1966 March-April Capital construction - Rome - Replacement data, 1966 41 17
1968 November-1969 May Capital construction - Rome - Specifications of labor and materials 41 18
1957 December-1958 May Capital construction - Commissioner's residence - Bathrooms 42 1
1965 October-1967 January Capital construction - Commissioner's residence - Driveway 42 2
1961 May-1962 January Capital construction - Commissioner's residence - Electric service 42 3
1964 September-1966 March Capital construction - Commissioner's residence - Fence 42 4
1959 June-November Capital construction - Commissioner's residence - Pump 42 5
1958 June-November Capital construction - Commissioner's residence - Paving roadway 42 6
1958 January-1965 July Capital construction - Commissioner's residence - Rehabilitation (general) 42 7
1958 February-1965 June Capital construction - Commissioner's residence - Septic tank and sewage disposal 42 8
1964 July-1967 August Capital construction - State Education Building - Clock system 42 9
1959 August-1961 October Capital construction - State Education Building - Annex - Equipment items 42 10
1965 February-1967 May Capital construction - State Education Building - Freight elevator #10 42 11
1962 August-1967 April Capital construction - State Education Building - Engine room instrumental panel board 42 12
1966 June-1967 December Capital construction - State Education Building - Lighting fixtures 42 13
1964 September-1967 February Capital construction - State Education Building - Sidewalks 42 14
1965 February-1967 April Capital construction - State Education Building - Vacuum pumps 42 15
1961 August-1962 June Capital construction - State Education Building - State Library - Archives building 42 16
1959 January-1967 February Capital construction - State Education Building - Fire protection 42 17
1962 August-1966 August Capital construction - State Education Building - Security cages 42 18
1964 June-1967 July Capital construction - Rome - Fire detection system 42 19
1959 March-1967 June Capital construction - Rome - Fire safety 42 20
1964 June-1966 January Capital construction - Rome - Floodlights 42 21
1961 December-1964 September Capital construction - Rome - Floors 42 22
1962 February-April Capital construction - Rome - Removal of hospital building #8 42 23
1965 May-1966 April Capital construction - Rome - Sanitary sewer line 42 24
1962 July-August Capital construction - Rome - Sidewalks 42 25
1959 January-1970 February Capital construction - Rome - Dormitories 43 1
1967 March-1970 February Capital construction - Rome - Dormitories 43 2
1967 June-1969 April Capital construction - Rome - Dormitories - Electrical work 43 3
1966 October-1969 March Capital construction - Rome - Dormitories - Elevator 43 4
1968 April-1970 January Capital construction - Rome - Dormitories - Equipment 43 5
1969 May-1970 January Capital construction - Rome - Heating 43 6
1967 January-1969 April Capital construction - Rome - Sanitary 43 7
1967 April Capital construction - Rome - Specifications of labor and materials 43
1962 November-1965 October Capital construction - Rome - Fallout shelter 43 8
1967 February-1969 January Capital construction - Rome - Heating service connections 43 9
1967 June Capital construction - Rome - Swimming pool 43 10
1966 May-1969 February Capital construction - Rome - Pre-primary building 43 11
1966 May-1968 September Capital construction - Rome - Pre-primary building - Electrical work 43 12
1967 April-June Capital construction - Rome - Pre-primary building - Elevator work 43 13
1966 May-June Capital construction - Rome - Pre-primary building - Food service equipment 43 14
1966 May-1968 May Capital construction - Rome - Pre-primary building - Heating work 43 15
1966 May-1968 May Capital construction - Rome - Pre-primary building - Sanitary work 43 16
1962 September-1967 March Capital construction - Batavia - Civil defense control center 43 17
1959 December-1965 July Capital construction - Batavia - Fallout shelter 43 18
1968 June-December Capital construction - Rome - Demolition-Phase II 43 19
1964 May-1968 May Capital construction - Rome - Pre-primary building - General 43 20
1960 November-1961 June Capital construction - Batavia - - Fire safety 1960 November-1961 June 43 21
1959 August-1967 January Capital construction - Batavia - Vehicle and equipment storage building 43 22
1962 May-1965 July Capital construction - Batavia - Resurfacing of Richmond Avenue 43 23
1967 January-1968 February Capital construction - Batavia - Vehicle and equipment storage building 43 24